The timeframe for substantial completion of paving, curb and median work from 48th to Lincoln is targeted for the second week of May. Substantial complete of project down to Sloat is set for the end of June.
Construction to the Great Highway continues. Thank you for your patience while these improvements are being made.
Work is still concentrated on the section of roadway starting at Lincoln through the end of the park heading north, and up Point Lobos to 48th Avenue (project map).
Sewer work continues between Lincoln and Balboa. You'll see the median in several sections has been moved and traffic is down to one lane in each direction. Work to install an irrigation system in those areas commences this week and will last about two weeks. This irrigation will be for the new planted materials along the
medians.
Construction to the Great Highway continues. Thank you for your patience while these improvements are being made.
Work is still concentrated on the section of roadway starting at Lincoln through the end of the park heading north, and up Point Lobos to 48th Avenue (project map).
Sewer work continues between Lincoln and Balboa. You'll see the median in several sections has been moved and traffic is down to one lane in each direction. Work to install an irrigation system in those areas commences this week and will last about two weeks. This irrigation will be for the new planted materials along the
medians.